NEW QUESTION # 94
Which records provide detailed, documented records of an applicant's personal history, background, and financial relationships?
- A. Legal action
- B. Civil litigation
- C. All of the above
- D. Civil lawsuit
Answer: B
NEW QUESTION # 95
Free float is the
- A. Difference between the early dates and late dates of an activity.
- B. Difference In float value of the critical path activities and the float value of the specific activity being analyzed.
- C. Difference between the early finish dates and late finish dates of an activity.
- D. Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.
Answer: D
Explanation:
Free float is a concept in Critical Path Method (CPM) scheduling that refers to the amount of time an activity's early start can be delayed without affecting the early start of any immediately succeeding activities.
* Option A refers to total float, which considers early and late dates of an activity.
* Option C also points to total float.
* Option D does not define free float.
Free float is critical for project planners as it provides flexibility in scheduling without impacting downstream activities.
NEW QUESTION # 96
How much Total Float does drafting the product manual have?
- A. 10 workdays.
- B. 0 workdays.
- C. 15 workdays.
- D. 5 workdays.
Answer: A
NEW QUESTION # 97
The concept that accepts the fact that the plaintiff may have contributed to his or her own injury, such as being in a restricted area or creating a disturbance or some hazard is known as:
- A. Control tactics
- B. None of the above
- C. Comparative fault
- D. Defensive control
Answer: C
NEW QUESTION # 98
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
- A. Tabular listing of activities showing duration, calendar ID, early and late dates
- B. Detailed listing of working days for each calendar used
- C. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID
- D. Assigned party responsibility for each work task
Answer: D
NEW QUESTION # 99
For which of these delays should an owner grant a time extension?
- A. Shop drawings and centrifuge delay.
- B. Differing site conditions at parking structure.
- C. Differing site conditions and centrifuge delay.
- D. Structural steel shop drawings.
Answer: B
NEW QUESTION # 100
Which approach is dealt with terrorists' personalities, their recruitment, and their induction into terrorist organizations, beliefs, attitudes, motivations and careers?
- A. Criminal approach
- B. Violence Approach
- C. Multifactor Approach
- D. Physiological Approach
Answer: D
NEW QUESTION # 101
Ideally a business should have four sets of backup files;
- A. with four set of files staying on-site and no set of files being stored off-site
- B. with one set of files staying on-site and three sets of files being stored off-site
- C. with three set of files staying on-site and one set of files being stored off-site
- D. with two of files staying on-site and two sets of files being stored off-site
Answer: B
NEW QUESTION # 102
The operations that are 'in-house', or controlled entirely by the company establishing security for its operations is called:
- A. Contract security operations
- B. Proprietary security operations
- C. Control operations
- D. Staffing operations
Answer: B
NEW QUESTION # 103
What signal the entry of persons into a facility or an area while the system is in operation?
- A. Protection alarms
- B. Access door
- C. Intrusion alarms
- D. Invasions
Answer: C
NEW QUESTION # 104
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?
- A. A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity
6002. - B. A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001
- C. A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag
- D. A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002
Answer: B
Explanation:
Logic Organization Requirement:
* Activity 6002 is required to begin 10 days after the start of Activity 6001.
* A start-to-start (SS) relationship with a 10-day lag effectively captures this requirement.
Exclusion of Other Options:
* Option B: Placing the lag on Activity 6002 introduces unnecessary complexity.
* Option C: Start-to-finish relationships are not appropriate for this situation.
* Option D: A finish-to-start relationship does not meet the requirement of aligning start times.
Verification with PSP Guidelines:The PSP Study Guide emphasizes using SS relationships with lags for activities that need staggered starts (Ref: PSP Study Guide, Chapter 2A: Relationships and Lags).
NEW QUESTION # 105
Worms take over computer memory and deny its use to legitimate programs.
- A. True
- B. False
Answer: A
NEW QUESTION # 106
What is a critical path method schedule?
- A. List of work to be accomplished by responsible party and when it is to be accomplished
- B. A network diagram of logically interconnected activities
- C. The timeline of the riskiest work
- D. A graphical means of showing the important work
Answer: B
Explanation:
Definition of a Critical Path Method (CPM) Schedule:
* CPM schedules are based on network diagrams that logically link activities, showing the sequence and dependencies between them.
* These schedules identify the critical path, which is the longest path through the network, determining the project's shortest possible duration.
Evaluation of Options:
* Option A: Incorrect. While CPM schedules do include tasks and timelines, the defining feature is the logical interconnection of activities.
* Option B: Incorrect. CPM schedules are not limited to "risky" work; they show all activities.
* Option C: Incorrect. CPM schedules use network diagrams, not just graphical representations.
* Option D: Correct. The network diagram is the key characteristic of CPM schedules.
NEW QUESTION # 107
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
- A. An out-of-sequence activity cannot resume until all predecessors are finished.
- B. It is calculated using the original logic.
- C. It is calculated using logic reflecting out-of-sequence progress.
- D. There is no such thing.
Answer: B
Explanation:
Retaining existing logic means preserving the original relationships and dependencies defined in the schedule.
Even if progress is recorded out of sequence, calculations adhere to the pre-established logic unless explicitly changed.
* Option B reflects adjustments for out-of-sequence progress but contradicts the original logic requirement.
* Option C imposes restrictions that do not align with typical CPM calculations.
* Option D is incorrect as the concept exists.
The PSP Study Guide discusses the importance of maintaining logic integrity in CPM scheduling.
NEW QUESTION # 108
The process of finding the person best qualified for the job in terms of both skills and personal integrity is known as:
- A. Inspection
- B. Screening
- C. Recruitment
- D. Vetting
Answer: B
NEW QUESTION # 109
Determine the correct formula and date for the late finish for Activity 2002.
- A. LS of 2003 less 1 day equaling to 05 Oct 2021
- B. LS of 2003 plus 1 day equaling to 07 Oct 2021
- C. LS of 2003 less 1 day equaling to 06 Oct 2021
- D. LS of 2003 less 1 day equaling to 06 Nov 2021
Answer: A
NEW QUESTION # 110
......
ASIS PSP certification is one of the most prestigious certifications in the field of physical security. The PSP stands for Physical Security Professional, and it is designed to test an individual’s knowledge and skills in managing, designing, and implementing physical security solutions. ASIS Physical Security Professional Exam certification is offered by ASIS International, which is the world's largest organization for security professionals. The PSP certification is recognized globally and is highly valued by employers and clients.